Current Projects

Trout Creek Bridge to
Ski Run Blvd

Caltrans is doing major construction on U.S. Highway 50 in South Lake Tahoe from Trout Creek Bridge to Ski Run Boulevard to add a storm drainage system to help protect Lake water quality, class II bike lanes, ADA-compliant sidewalks and pedestrian lighting. For details on the projects as it moves along, please click below to access the project update map.

October 18
  • Approximately 55% of the Trout Creek Project work has been completed.
  • 1.1 miles of the roadway from Trout Creek to west of Altamira has new curb, gutter and paved roadway.
  • The stormdrain filters are near completion -- two are expected to be operational in October.
  • The drainage basins in the campground area are excavated to grade and are operational.
  • Walkways and driveways are work in progress. 
  • Critical work to winterize will continue through the month.



August 22 - Weekly Project Update

September 19-October 7 - Weekly Project Update

Completed Project


Paving job complete at Squaw Valley